Restoration works of the North breakwater of Ventspils Freeport, where LLC "CHR Design Solutions" is responsible for authors field supervision, started in March 2019.

Construction works that have already been started:

  • replenishment of tetrapods on breakwater (5t and 13t);
  • addition of concrete cubes weighing 45 tons each;
  • construction of inverted filter;
  • construction of electrical and signal cable lines with total length of ~50km.