Client: Salacgriva Port Authority
Start date: May 2025
Completion date: August 2026
Following a public procurement procedure, Salacgrīva Port Authority entered into a contract with the “CHR-VM” consortium, comprising SIA “CHR Design Solutions” and SIA “V & M BŪVE”.
SIA “CHR Design Solutions” was responsible for the overall project management, preparation of the construction design and provision of designer’s supervision services. As part of the project, a new 60-metre coastal fishing pier was constructed at Kuiviži Port, replacing the infrastructure previously used for mooring fishing boats.
The works included the construction of the new pier structures, improvement of the related port infrastructure and provision of the required navigational depth alongside the pier.
The completed project improved the port’s capacity to service the fishing fleet, enhanced navigational safety and pier functionality, and contributed to the sustainable development of the Kuiviži Port area.
The pier was commissioned on 7 August 2026.